Discover the
Eastmain‑Sarcelle‑Rupert complex

A little history

Located in the Nord du Québec administrative region, the Bernard Landry (previously Eastmain‑1‑A) and Sarcelle generating stations, the construction of which began in February 2007, were commissioned in 2012 and 2013. The partial diversion of the Rivière Rupert was completed in November 2009.

Main facilities

Aerial view of Bernard‑Landry and Eastmain‑1 generating stations

The Eastmain‑1‑A/Sarcelle/Rupert project increased Hydro‑Québec’s output by about 8.7 TWh with the following facilities:

  • Bernard‑Landry generating station (originally Eastmain‑1‑A), installed capacity of 768 MW, located near Eastmain‑1 generating station
  • Sarcelle generating station, installed capacity of 150 MW, located at the outlet of Opinaca reservoir
  • The partial diversion of the Rivière Rupert with four dams, an instream flow release structure and a system of canals to carry some of the water from the Rupert to the two new generating stations, then to Robert‑Bourassa, La Grande 2‑A and La Grande‑1 generating stations
  • Two diversion bays upstream of Rupert dam, covering about 346 km2 and connected by a 2.9‑km-long tunnel
  • Eight hydraulic structures (weirs, spurs and rock blankets) downstream of Rupert dam to maintain the water level along nearly half of the Rupert.

Advantages and description

Sarcelle jobsite for construction of the Sarcelle generating station

Construction of Bernard‑Landry generating station

Advantages

Optimization of the generating capacity

The main advantage of the Eastmain‑1‑A/Sarcelle/Rupert facilities is that they optimize the generating capacity of some existing generating stations, adding 8.7 TWh to the generating fleet’s output. Once it has driven the turbines of Eastmain‑1 or Bernard‑Landry and Sarcelle powerhouses, the water continues on to Robert‑Bourassa, La Grande‑2‑A and La Grande‑1 generating stations.

Integrating the power generated

To integrate the output of the new generating stations into the grid, a 315‑kV line was built between Eastmain‑1 and Bernard‑Landry switchyards (in 2011), and another between Sarcelle and Eastmain‑1 switchyards.

Bernard‑Landry generating station and the switchyard in winter

Description

Generating stations

Bernard-Landry generating station (originally Eastmain‑1‑A), with an installed capacity of 768 MW and a maximum flow of 1,344 m3/s, is located near Eastmain‑1 generating station. Sarcelle generating station, with an installed capacity of 150 MW and a maximum flow of 1,380 m3/s, is located at the outlet of Opinaca reservoir, and has a mean annual diverted flow of 452 m3/s.

Other facilities:

  • Partial diversion of the Rupert includes four dams, an instream flow release structure and a system of canals to carry some of the water from the Rupert to the two new generating stations, then to Robert‑Bourassa, La Grande 2‑A and La Grande‑1 generating stations
  • 74 dikes
  • 2 diversion bays upstream of Rupert dam, covering about 346 km2 at their maximum level and connected by a 2.9‑km‑long tunnel
  • 8 hydraulic structures (weirs, spurs or rock blankets) downstream of Rupert dam to maintain the post-diversion water level along nearly half of the Rupert (see Map 3), all of which were completed in 2010
  • 1 spillway on the Rupert at the dam site, which also controls the instream flow
  • 5 other instream flow release structures built into some of the retaining structures in the diversion bays (Nemiscau‑1, Nemiscau‑2, Ruisseau‑Arques, Lemare and LR‑51‑52)
  • 1 2.9‑km‑long transfer tunnel between the two diversion bays, where the maximum authorized flow is 800 m3/s
  • 9 canals (4 in the forebay and 5 in the tailbay) about 7‑km long, to facilitate adequate water flow in the different parts of the diversion bays

History and key moments

Construction of the transfer tunnel

Eastmain‑Sarcelle‑Rupert Complex

1993: The Conseil exécutif du gouvernement du Québec issued an order-in-council authorizing Hydro‑Québec to build the Eastmain‑1 hydroelectric project. The Ministère de l’Environnement (MENV)1 then issued a certificate of authorization to build the generating station under section 22 of the Environment Quality Act (EQA)

1 Now called the Ministère de l’Environnement et de la Lutte contre les changements climatiques, de la Faune et des Parcs.

Infrastructures and facilities

To build the complex, Hydro‑Québec had to set up temporary and permanent infrastructures and facilities:

  • 137 km of access roads to the structures
  • A permanent, 40‑km road between Muskeg substation and the Nemiscau‑Eastmain‑1 road
  • Temporary work camps to house workers
  • Work areas, borrow pits, etc.
1 of 4

View of Eastmain‑1 and Bernard‑Landry generating stations

Workers at the Eastmain‑1‑A‑Sarcelle‑Rupert jobsite

Sarcelle workcamp

Eastmain workcamp